Timeframe

Milestones of the project

 

  • The project has started in October 2010.
  • The Everest Clean Up Camgaign was implemented in April and Mai 2011 and ended successfully with the collection of more than 8 tons of rubbish.
  • In the actual project phase all partners are working on the implementation of a sustainable waste management system in the Everest region.
  • By autumn/winter 2013 the project activities will be completed and evaluated and provide a basis for further activities.
  • In may 2014 the first project activities became finished and evaluated. The results served as a basis for further actions.

  • In september 2015 the project was completed.